1. Temporary friction, not structural risk
- Texas contacts view large load friction as temporary, preserving long-term demand thesis.
Texas grid headwinds are overblown and short-lived, leaving SRE's growth trajectory intact.
Texas regulatory scrutiny is intensifying and may harden into multi-year permitting constraints, raising execution risk for SRE.
Texas contacts generally view current friction around large loads and transmission as temporary, with infrastructure still needed to support growth.
The base case remains for delays of months rather than years, with Batch Zero and load growth ultimately proceeding.
AEP/CNP/SRE/VST: Mizuho says Texas grid overhang is mostly timing/noise, though 2027 legislative risk is rising
Elevated political and regulatory noise is expected into the 2027 legislative session, with Texas Senate committees scrutinizing transmission siting, property rights, and data center impacts, which could tighten permitting and timelines.
Research through 2026-09-21 · 2026-09-21 to 2026-09-21 · 1 source reports.